[Bug][jenkins] Incremental collection skips the stages of builds that finish after the next sync

未关闭
#9,177 1 条评论 0 个 reaction 已指派 0 人 在 GitHub 查看

维护者通常 1 天内回复

还没有人认领这个 Issue。

评估

难度
3/5
预计耗时
1-2 天
新手友好度
76/100
Issue 类型
缺陷
描述清晰度
描述清楚
活跃度
活跃
技术栈
go
领域
ci-cd

调研方向

Start in backend/plugins/jenkins/tasks/stage_collector.go and inspect the incremental filters in both the single-job and multi-branch collectors. Reproduce a build that spans two collections, then verify that an incremental run finds its stages and that full and incremental collections produce the same stage records.

由索引模型根据 Issue 内容生成。

描述

Search before asking
  • I had searched in the issues and found no similar issues.
What happened

With incremental collection, collectApiStages never collects the stages of a Jenkins build that started before the previous collection and finished after it. Those builds end up in _tool_jenkins_builds with a result, but with no rows in _raw_jenkins_api_stages / _tool_jenkins_stages, so their deployment stages never become cicd_tasks and the deployments are missing from DORA.

Cause (backend/plugins/jenkins/tasks/stage_collector.go, both the single-job and the multi-branch collectors):

if apiCollector.IsIncremental() && apiCollector.GetSince() != nil {
    clauses = append(clauses, dal.Where(`tjb.start_time >= ?`, apiCollector.GetSince()))
}

The build collectors skip builds that are still running (buildObj["result"] != nil), so a build is stored the first time it is collected finished. For a build that started before since and finished after it, that happens in a later run, and the stage collector filters it out by start_time in that run and in every run after it. Nothing reports it.

This is common in pipelines that wait on an input step, e.g. a "rollback?" or "deploy to production?" approval left open for hours or days after the deploy.

Evidence from our instance (v1.0.3-beta15, 190 multi-branch scopes, daily collection):

Build duration Builds with stages, first (full) collection Builds with stages, incremental runs since
< 6 h 508 / 561 680 / 711
6–24 h 25 / 25 5 / 68
> 24 h 698 / 814 13 / 389

For example, front-channel/master#111 (SUCCESS, 148 h) is in _tool_jenkins_builds and has no row in _raw_jenkins_api_stages. The collector is unchanged on main.

What do you expect to happen

An incremental run collects the stages of every build that became available since the previous run, i.e. every build that finished since then, whenever it started. A full and an incremental collection should produce the same stages.

How to reproduce
  1. Jenkins scope with incremental collection (any sync after the first).
  2. Start a pipeline build that waits on an input step, and let a collection run while it waits.
  3. Answer the input after that collection so the build finishes, then run another collection.
  4. The build is in _tool_jenkins_builds, but _tool_jenkins_stages has no rows for it.
Anything else

Proposed fix, PR to follow: filter on the finish time, tjb.timestamp + tjb.duration >= since. Both columns are milliseconds, so it is plain arithmetic on MySQL and PostgreSQL, no dialect-specific date functions. It is a superset of the current condition (duration ≥ 0).

Version

v1.0.3-beta15 (collector unchanged on main)

Are you willing to submit PR?
  • Yes I am willing to submit a PR!
Code of Conduct
主要语言
Go
星标
3.1k
派生
812
平均合并
2 天 8 小时
30 天内合并 PR
50

环境准备

我们还没有检查这个项目的环境配置文件。先看它的 README,通用步骤见我们的新手贡献指南。

从这里开始

  1. 先读完整个 Issue,再读项目的贡献指南。
  2. 在 Issue 下留言说明你要接手 —— 这能避免两个人做同样的事。
  3. Fork 仓库,在一个分支上完成修改。
  4. 提交 Pull Request,并在描述里引用这个 Issue 编号。

apache/devlake 的其他 Issue

查看 apache/devlake 的全部 Issue

相似的 Issue

更多 Go Issue

把新 issue 发到你的邮箱

精选适合新手参与的 GitHub issue 摘要。